GENERAL REQUIREMENTS
The following is a checklist, which should be used as a guide to assist
you in preparing your project for the installation of your underground service.
Once you have completed these items, Central Lincoln will install your service line and
meter.
Ask us where your service line will originate. Call
your nearest service office and ask to speak to an engineer
(see SECTION A
- General Information).
Determine an acceptable location for your meter base
(see SECTION A - General Information).
Dig a trench and provide conduit from your meter
base to the service hand-hole location, then to the location where your
service will originate.
Install Central Lincoln-provided service hand-hole
(HH-14 or
HH-20), and Central Lincoln-provided pull string.
Install your service equipment.
Have the local electrical inspection agency
(see
SECTION A - General Information)
approve your service installation.
Call Central Lincoln’s service office and notify them that you
are inspected and have a "green tag" sticker on your meter base.
GETTING STARTED
The first step when installing a new underground service is to contact
our nearest service office and ask an engineering technician where your service
will originate.
Next, determine the location of your meter base. As stated previously, your
meter base should be located outside and on the front, or within 4 feet of it on
the side closest to normal public access (see Figure A-1).
When choosing your meter base location, be sure to consider the types of
terrain where your conduit will be buried. You are required to provide, install
and maintain conduit, and Central Lincoln is responsible for repairing service line if it
ever fails. You must use 3" inch Schedule 40 PVC electrical grade conduit unless
dictated by other ordinances and approved by Central Lincoln. You will also need a service
hand-hole. 
Customer-installed continuous conduit runs shall not contain more than three
90-degree elbows, or a maximum of 270 degrees of long radius bends, unless
pre-approved by an engineering technician.
Conduit runs of more than 50 feet, or containing more than two 90 degree PVC
elbows shall have a Central Lincoln-provided pullstring installed.
SERVICE EQUIPMENT
INSTALLATION REQUIREMENTS
After you have determined the meter base location, the service line
route, the size of the service you want (200 or 400 amp), you are ready to begin
installing your service equipment.
There are three ways this equipment can be installed:
Flush mounted (see Figure C-4)
Surface mounted (see
Figure C-5)
Pedestal mounted (see
Figures C-6 & C-7)
When installing your service equipment, make sure that you install your meter
base so that the center of the meter will be between 5 and 6 feet above finished
grade.
TRENCHING REQUIREMENTS
You are to provide a trench, 24 inches deep, from your meter base to the
service hand-hole
(HH-14 or HH-20). Your trench will then continue, at 36
inches deep, to the pole, transformer, or secondary hand-hole where your service
will originate. The trench must have a level, flat bottom, void of shifting
soil. The trench must be free of all sharp rock and construction debris. There
must be at least 12 inches of separation from all other utilities within the
trench (see Figure C-3). The trench must be a minimum of 3 feet from
sewer and gas, 5 feet from septic tanks and 10 feet from any drain fields.
When trenching to a transformer, or any energized structures, don’t use any
digging equipment other than a hand shovel within 5 feet of transformer.
NOTE: For underground service installations, don’t dig or install any
conduit or wire into an existing Central Lincoln vault without assistance from a
qualified Central Lincoln employee. (Access to Central Lincoln equipment
by persons other than Central Lincoln employees is prohibited.) Remember,
do not dig under the transformer.
Also remember:
Call before you dig: 811 (see SECTION A).
CONDUIT
Customer will provide conduit and conduit elbows from the meter base to
the service hand-hole (generally 2" - see NEC). Continue with a second
set of 3" conduit and conduit elbows from the service hand-hole to the Central
Lincoln
source (pole, transformer or secondary hand-hole). The conduit will be Sched
ule
40 PVC electrical grade unless otherwise required by the engineering technician,
road right-of-way administrator, or electrical inspector (see Figures C-1,
C-2).
You are required to keep the conduit clean and clear of debris and water. End
plugs will be provided by Central Lincoln, and you are required to have these
installed.
Do not install conduit into energized equipment such as a transformer or an
energized hand-hole.
At a transformer, or energized hand-hole location, you will need to call our
service office to coordinate our being at the site to assist you in installing
the elbow, pullstring and backfill.
You will need to install all conduit, pullstring, service hand-hole,
trenching and backfill from the meter base to the Central Lincoln source
(pole, transformer, secondary hand-hole).
SERVICE HAND-HOLE
You’ll need to pick up and transport a service hand-hole from Central Lincoln
to your site. (Ask engineering technician for details.) If your service
is a 200 amp single meter base installation you can pick up the HH-14 at your
local service office.
If you have a bigger meter base, or more than one meter, you’ll need to pick
up a larger service
hand-hole from your local Central Lincoln warehouse. Ask
your engineering technician for warehouse location and hours of service.
It is your responsibility to install the service hand-hole in your trench
(see Figures C-1, C-2 & C-8), within 10 feet of the meter base. The lid portion
of the service hand-hole must be above the finished grade.
Two conduit elbows are required inside the service hand-hole (one from the
meter and one from the pole, transformer or secondary hand-hole). The two
elbows are to be 2" above the bottom of the dirt floor of the hand-hole, and
centered in the short side of the hand-hole (see the Top View in Figures C-4-
C-5 & C-8).
Do not install the service hand-hole in a concrete area unless you receive
prior instruction from an engineering technician. If the service hand-hole fills
with water, you are required to provide adequate drainage, possibly excavating a
larger area and underlying the service hand-hole with gravel.
Central Lincoln crews must have easy access to the hand-hole cover at all
times. Hand-hole must not be covered with pavement, deck, landscaping, etc.
PULLSTRING
Pull string is to be blown in after the sections of the conduit have been
glued and the glue has properly dried. Make sure the pull string does not get
glued to the conduit. You will not be required to install pull string unless
your trench is over 50 feet long, or has more than 180 degrees in elbows.
BACKFILL
After you have installed the trench, conduit, service hand-hole and
pullstring,
you’re ready to call your service office for a trench inspection.
You may use the original trench material for backfill, after the inspection,
if it is clean (does not contain rock, construction debris, etc). Otherwise,
sand is the preferred backfill.
FINAL
INSPECTION
All Central Lincoln underground box and duct systems done by customers, contractors
or builders will require a final inspection and approval by a Central
Lincoln Operations
Department inspector. The Central Lincoln inspector must approve all jobs requiring
trenching before the Central Lincoln service or line crew can be dispatched to do the
electrical installation.
Items
owned and installed by customer
(Figs. C-4, C-5)
1.
Meter
base.
2. Insulating
bushing and lock nut.
3. Terminal
adapter.
4. Conduit
strap.
5. Service
entrance conduit as specified by NEC or local electrical inspector.
6. 90However, Central Lincoln will find and repair damage to your existing
direct-buried underground service, and we will continue to do so as necessary
at no cost to the customer. These direct-buried failures cause outages that
are frustrating for the customer and expensive for Central Lincoln to repair,
so we encourage customers with direct-buried service to upgrade to
conduit-based systems.
Normally, a customer installing new underground service must provide all
the conduit necessary for the installation. But as an incentive to upgrade,
Central Lincoln will provide the necessary wire, conduit, 90 degree ells,
HH-14 hand-hole, and pull string from our point of service to the hand-hole
near your existing meter base. The customer is still required to provide any
trenching necessary.
If you’re interested in upgrading from a direct-buried system, please
contact Central Lincoln before doing any of the work. A Customer Engineering
Representative will meet with you to determine the proper route for any
conduit installation before you dig. And an inspection is necessary of all
conduit and substructure installation before trenches are back-filled.